ESE Restore Vandalised Site.

ESE Restore Vandalised Site.

ESE were called out to a site in Bolton to inspect the high voltage network after unwanted visitors vandalised site. The vandalism resulted in the site having no power, and the high voltage equipment being damaged. When ESE attended site the majority of the high & low voltage cables had been removed, and the transformer and switchgear had been badly vandalised.

ESE removed all the vandalised equipment from site and installed a new 5 panel Schneider Electrical board. This consisted of two Schneider Electrical SE6-S1, and three Schneider Electrical CE2-T7.

ESE also installed three new ESE 1000KVA 11000/433 oil filled EU Directive transformers.

The new substation was then rebuilt with a new palisade fence to stop any unwanted guest from any future visits.